Electricity being restored in East Berbice after more than 45 hours of blackout
Full story
Guyana Power and Light Inc. reported that work at the Canefield substation was finished by Saturday night. Restoration of electricity began incrementally around 6:48 PM. The company stated that power is returning for customers between Canefield and Williamsburg. Restoration also includes the area from Canefield to Kortberaadt. This follows a blackout that lasted more than 45 hours.
Last Updated on Saturday, 21 November 2026, 18:56 by Written By Denis Chabrol The Guyana Power and Light Inc. (GPL) said Saturday night at about 6:48 PM that works at the Canefield substation have been completed and incremental restoration has commenced. The power company said customers in Canefield to Williamsburg and Canefield to Kortberaadt would […]