ZESCO FACES KARIBA WATER ALLOCATION LIMIT IN 10 DAYS

zambianobserver.com · world
Full story

ZESCO may run out of its 2026 water allocation for electricity generation at the Kariba North Bank Power Station within 10 days. Currently, only 3.75 percent of the allocation remains. This information surfaced during a visit by a minister to the Zambezi River Authority.

ZESCO FACES KARIBA WATER ALLOCATION LIMIT IN 10 DAYS By Best Jere ZESCO could exhaust its 2026 water allocation for electricity generation at Kariba North Bank Power Station in about 10 days, with only 3.75 percent of its allocation remaining. This came to light during a familiarisation visit to the Zambezi River Authority by Minister […] The post ZESCO FACES KARIBA WATER ALLOCATION LIMIT IN 10 DAYS first appeared on The Zambian Observer .

Read full article → Compare