PICS: Inanda residents still waiting for homes as R149m eThekwini housing project stalls
Full story
A housing project in Inanda has stalled despite a budget of 149 million rand. Only 73 of the 311 planned homes in the Namibia 8 project are finished. Residents in temporary housing report defects in the buildings. They are also dealing with water problems and poor sanitation.
Only 73 of 311 planned homes have been completed at eThekwini’s Namibia 8 housing project in Inanda, while residents relocated to temporary accommodation report poor sanitation, water problems and building defects.