DOE and NNSA approve $23.5 billion Savannah River plutonium plant plan with 2038 deadline

kenya-today.com · world
Full story

The U.S. Department of Energy and the National Nuclear Security Administration have established a budget for a plutonium processing facility at Savannah River. The financial baseline for the project is set at $23.5 billion. Officials have targeted December 2038 as the deadline for completion.

The U.S. Department of Energy and the National Nuclear Security Administration have set a $23.5 billion baseline for the Savannah River plutonium processing facility, targeting completion by December 2038.