Dukung Pertumbuhan Industri, PLN Rampungkan Energize GI KEK Kendal 147 Hari Lebih Cepat

republika.co.id · world
Full story

PT PLN completed the energizing of the 150 kV substation for the Kendal Special Economic Zone. The project was finished 147 days ahead of schedule. This effort was managed through the Central Java Development Main Unit. The work included the installation of overhead tension lines to support industrial growth.

PT PLN (Persero) melalui Unit Induk Pembangunan Jawa Bagian Tengah (UIP JBT) berhasil melakukan energize Gardu Induk (GI) 150 kV Kawasan Ekonomi Khusus (KEK) Kendal beserta Saluran Udara Tegangan...

Read full article → Compare